2018/037: Refusal to grant exemption from the requirement to obtain a building consent for proposed seismic strengthening work
Document
About this determination
Summary
This determination considers the authority’s refusal to grant an exemption from the requirement to obtain a building consent under Schedule 1(2)(a) for seismic strengthening work. The determination discusses the types of matters that an authority must turn its mind to when considering whether to grant an exemption and the information provided in this case that would allow the authority to consider an application for an exemption.