2018/020: Refusal to issue a code compliance certificate for a house with rammed-earth walls

Back to determinations register

About this determination

Summary

This determination considers the compliance of the second stage of a house built with rammed-earth walls used as a structural element and as a cladding.  The determination considers the compliance of the as-built work, the on-going maintenance of the rammed-earth walls, and whether the authority was correct in declining to issue a code compliance certificate for the work.

View all determinations on this topic

Back to determinations register

This information is published by the Ministry of Business, Innovation and Employment’s Chief Executive. It is a general guide only and, if used, does not relieve any person of the obligation to consider any matter to which the information relates according to the circumstances of the particular case. Expert advice may be required in specific circumstances. Where this information relates to assisting people: