2016/018: Regarding the issue of a notice to fix for a two-cell earthship building
Document
About this determination
Summary
This determination considers whether a two-celled rammed earth building constructed without consent was exempt under Schedule 1 and whether the authority was correct to issue a notice to fix. The determination discusses the remedies provided for in the notice, and discusses issues relating to an application for a certificate of acceptance.