2015/031: Refusal to issue compliance certificates for a 12 year-old shop, 8 year-old toilet block and alterations to a building consent
Document
About this determination
Summary
Discussed building work exempt under Schedule 1 for which building consent is not required, compliance of building work with the Building Code in force at the time of construction, and amendment to a building consent to modify the durability periods and remove building elements that no longer exist. Also discussed the need for a certificate of acceptance for alterations carried out without building consent when consent was required.