Previous determinations

Determinations are made by MBIE on matters of doubt or dispute to do with building work. Rulings are legally binding, but only in relation to each case.

Previous determinations may provide some useful guidance for those faced with similar problems, but note that individual circumstances may vary.

You can also search for Determinations on Building CodeHub

Find a determination

Applying filters will narrow down your search results

Find a determination

Search results

1893 Determinations match your query
Show detailed results

2016/001: Refusal to issue code compliance certificates for a 15-year-old extension to a house with weatherboard and brick veneer cladding

This determination considers the authority’s decision to refuse to issue a code compliance certificate: the grounds for the refusal were the authority’s concerns regarding the weather-tightness and durability of the exterior envelope, and the structural performance of the foundation wall.  The determination reviewed the reasons given for the refusal and considered whether the items identified in the refusal comply with the Building Code.

About this document

2015/085:Regarding the authority’s exercise of its powers of decision in relation to a building consent application for an earthquake-prone building

This determination considers the authority’s decision to refuse to issue a building consent for alterations to an existing earthquake-prone building.  The alterations were for an internal fitout on the ground floor of the three-storey commercial building.  The determination considers the authority’s policy on earthquake-prone buildings in relation to the proposed work, and some matters in relation to the policy itself.  Detailed discussion on the policy will follow in a further determination. 

About this document

2015/084: Determination regarding the code compliance of fixings to plywood cladding on a 9-year-old house

This determination considers the compliance of nailing to plywood cladding to a house located in a sea spray zone: galvanised mild steel nails had been installed instead of stainless steel nails.  The determination considers the compliance of the plywood in relation to Building Code Clauses B1 Structure and E2 External moisture, and the remedial work done to date by the owner.

About this document

2015/083: Regarding the refusal to issue a code compliance certificate for a 16-year-old house

This determination considers the authority’s decision to refuse to issue a code compliance certificate: the grounds for the refusal were the authority’s concerns regarding the weather-tightness and durability of the exterior envelope, and the performance of a concrete floor slab and the subfloor space beneath with respect to structure and durability.  The determination reviewed the reasons given for the refusal and considered whether the items identified in the refusal comply with the Building Code.

About this document

2015/082: Regarding the authority’s exercise of powers in issuing an earthquake-prone building notice for a multi-storey unreinforced masonry building

This determination considers whether the authority correctly issued an earthquake-prone building notice for a multi-storey unreinforced masonry building. The determination also discusses the relationship between the legal test under section 122 of the Building Act 2004, the authority’s earthquake-prone building policy and the engineering methodology used at the time the earthquake-prone building notice was issued.

Note: This determination is subject to appeal. 

About this document

2015/081: Regarding the authority’s exercise of powers in issuing an earthquake-prone building notice for a multi-storey reinforced building

This determination considers whether the authority correctly issued an earthquake-prone building notice. The determination also discusses the relationship between the legal test under section 122 of the Building Act 2004, the authority’s earthquake-prone building policy and the engineering methodology used at the time the earthquake-prone building notice was issued.

About this document

2015/080: Regarding the refusal to issue a code compliance certificate for a 14 year-old prefabricated outbuilding

This determination considers the authority’s decision to refuse to issue a code compliance certificate; the grounds for the refusal were the authority’s concerns regarding the performance of the exterior cladding in terms of weathertightness and durability. The determination reviewed the reasons given for the refusal and considered whether the items identified in the refusal comply with the Building Code.

About this document

2015/079: Regarding the code compliance of CCA treated laminated veneer lumber

This determination discusses the pathway to establishing compliance with Clause B2.3.1 for laminated veneer lumber CCA treated in accordance with AS1604.4:2012 and used as structural framing members in situations where hazard class H3.2 or less would be used.

About this document

2015/078: Regarding the refusal to issue a code compliance certificate for a 9 year-old house with mixed claddings

This determination considers the authority’s decision to refuse to issue a code compliance certificate; the grounds for the refusal were the authority’s concerns regarding the performance of the exterior cladding in terms of weathertightness and durability. The determination reviewed the reasons given for the refusal and considered whether the items identified in the refusal comply with the Building Code.

About this document

2015/077: Regarding the authority's exercise of its powers of decision in requiring notice of a change of use

This determination involves two adjoining household units. The determination discusses whether the Building Code obligations relating to fire separation apply given the age of construction and whether there has been a change of use.

About this document

This information is published by the Ministry of Business, Innovation and Employment’s Chief Executive. It is a general guide only and, if used, does not relieve any person of the obligation to consider any matter to which the information relates according to the circumstances of the particular case. Expert advice may be required in specific circumstances. Where this information relates to assisting people: